September 12, 2016
Here's our monthly construction progress update, courtesy of Jeremy Wright, our construction project manager for one of the largest projects we've ever undertaken as a Design-Builder the Seaboard - Triumph Foods Pork Processing Plant in Sioux City, Iowa.
What you see here are few aerials of the 245-acre site showing our construction progress which Jeremy describes thusly,
'We are currently working to enclose the exterior of the building as Pre-cast construction has finished on the kill floor and is about 50% of the way complete in rendering. Work on the insulated metal panel walls continues to progress at numerous locations. In addition, underground plumbing continues to progress along with masonry on the interior as we begin to pour barn and cut floor slabs. Lastly, on the exterior - we are working on the site utilities continues as well as paving of the North West parking lot.'
The 750,000 square foot Seaboard Farms Triumph Foods facility is budgeted at $264M and is scheduled to be completed mid-2017.